As a result of this work, the aforementioned streets will be closed to traffic in phases. Due to weather conditions, the work has been rescheduled for 11/6/2025. 

Traffic controllers will be present during this closure/work.

The work consists of applying a wearing course to the road surface. This is thin layer of crushed stone chippings (gravel). Two colors (grit) will be applied. Between the application of the first color and second color is about a 4 weeks (two rounds of implementation). 

Applying wearing courses is a weather-dependent activity, in case of rain and/or wet road surface, the work will not take place. This work will then be rescheduled for Wednesday 11/6/2025. Application of the second color is scheduled for Friday 4/7/2025. Spare day is then Friday 18/7/2025.