Early Application for Electrical Connections

Update: Pre-registration for power connection applications closed 

The deadline for the 'early application for electricity connection' scheme has expired. Pre-registration closes on Tuesday, September 29, 2026. It is no longer possible to register new projects for this prioritization.

Order list established

The submitted projects that meet all Requirements those that meet the criteria are included in the final priority list. You can download and view the ranking list as an attachment at the bottom of this page.

Background of the methodology

All municipalities in the Netherlands have been instructed by the central government to infringe housing and education projects for the next 10 years Map to bring about. With this inventory, grid operators (such as Liander) gain faster insight into the expected demand for electricity. This allows them to better take this into account when planning and allocating the available capacity on the power grid.

The 'apply for electricity connection earlier' procedure applies exclusively to new-build homes (from a single home up to and including an entire residential area) and educational housing.

More Information and Questions

If you have questions about the 'apply for electricity connection earlier' procedure, please first check the answers to the most frequently asked questions and the information on these websites: 

Can't find your answer here? Please send an email toRinze.Bargerbos@opsterland.nl. 