MFC De Finne
There will be a new child center on Vlaslaan in Beetsterzwaag: MFC De Finne. This is where the school and Kinderwoud childcare will have a place. The soccer club is due for a new canteen and changing rooms. These will also come in the new building. MFC De Finne will be built on Vlaslaan in Beetsterzwaag, on the practice field of V.V. De Sweach. A nice central spot, right next to the village hall, the library and De Buorskip.
Neighborhood meeting
A neighborhood meeting was organized by the school, childcare organization and the soccer club in July 2024. During this neighborhood meeting, the VO (Preliminary Design) was presented to local residents and parents/caregivers of the children. In addition, special attention was paid to traffic and parking around the new MFC.
The preliminary draft
The preliminary design is not yet sufficient for the permit application. For this, all components must first be definitively coordinated. During the VO, the construction method is determined, the materials chosen and how the building can be built efficiently figured out.
The following points were incorporated into the VO:
- Architectural drawings (situation, floor plans, facades, sections)
- Wall and roof structure are specified
- The construction methodology is incorporated into the drawings
- 3D visualizations now include proper materialization and shapes.
The final design
- The VO is now being developed into a Final Design (DO). In the final design, the materials to be used are determined. The wall structure is fixed, along with the dimensions of the building. The materials will be further specified as will the drawings.
- Architect chooses all final materials
- The installation consultant chooses all installations and elaborates them on (3D) drawings.
- The structural engineer goes to work on these drawings to calculate the load-bearing capacity of the structure in the building.
- Based on the final material, plant and structural designs, the building physics consultant can get to work on the necessary calculations of:
- Ventilation moisture and indoor environment
- Daylight and artificial light
- Acoustics
- Fire Safety
- Sustainability and energy
- The municipality receives the final design for the environmental permit.
Planning
If all goes well, the contractor will be selected in early 2025 and construction will then start in the second half of 2025, which will take about a year.
Impression
Newsletters
- Read for Newsletter MFC De Finne - March 2024.pdf with ReadSpeaker docReader
- Read for Newsletter February 2023 with ReadSpeaker docReader
- Read for Newsletter February 2022 with ReadSpeaker docReader
- Read for Newsletter April 2020.pdf with ReadSpeaker docReader
- Read for Newsletter July 2019.pdf with ReadSpeaker docReader
- Read for Newsletter September 2018.pdf with ReadSpeaker docReader
Document download information:
- You can open a PDF file in various PDF readers, such as Adobe Reader.